Tasks Planning
What is "Tasks Planning" ?
The "Tasks Planning" report is represented in the form of a GANTT, allowing you to display the planning of your tasks on the chosen perimeter with the selected axis grouping.
User case example :This report can be used to track your tasks's progress with offset informations and the display of progress' percentage to provide additional information.
How is the slide built ?
The slide is built in 4 zones, represented by the orange zones on the image above: The slide is built in 4 zones, represented by the orange zones on the image above:



Additional parameters
Parameter* | Description |
Display chart legend | Allows you to display the schedule's colored legend |
Display item period | Allows you to display a bar to show the object's period on the schedule |
Display today position | Allows you to add a line representing the current date |
Display dependencies | Allows to display the dependencies between 2 elements on the schedule |
Display slippages | Allows you to display date offsets between the original end date and the current end date |
Display holidays | Allows to display holidays, requires a resource field or project manager field to be defined in axis |
Textbox borders format | Allows you to customize the axis' edges (zone 3) with rounded or unrounded corners |
Action milestone format | Allows you to choose the milestones' format (circle, diamond or triangle) |
Milestone label | Allows you to choose the milestone's label to be displayed to add the date or progress for example |
Milestone color mode | Allows you to choose the milestone's color according to either the status or meteo |
*Click on any parameter to get more informations about its usage
which level is it available at ?
- Project hierarchy : Business Line, Project, Workpackage
- Resource : Entity
- Axis : Business lines grouping, Projects grouping, workpackages grouping
Tips
- Nothing displaying ? : Check that you have chosen at least one axis, as well a the chosen period. If you do not display "item period", only the elements that are due in the chosen period will be displayed